Install CNG Station

Contract Number
MS08069
MSRC Award
$225,000.00
Project Background

The Perris Union High School District (District) purchased 23 new CNG Buses for student transportation. The transportation service providor, Hemet Unified School District, was fueling the buses at their CNG station in Hemet in order to transport Perris Union High School District Students. A CNG station at the PUHSD Transportation yard was needed to more efficiently run our student transportation.

Emission Tons CO Annual
0.00
Emission Tons CO Total
0.00
Emission Tons NOX Annual
0.00
Emission Tons PM Annual
0.00
Emission Tons PM Total
0.00
Emission Tons Rog Annual
0.00
Emission Tons Rog Total
0.00
Other Information
The implementation of alternative fuel infrastructure is an essential element of a low emission school bus strategy. It is convention, however, to apply the emission reductions attributable to the alternative fuel strategy to the low emission buses as opposed to the refueling apparatus. However, it should be recognized that the overall low emission bus strategy is contingent on the availability of convenient alternative fuel refueling station.
Project City
Perris
Project Cost Description

632541.00

Project Implementation

After being awarded the contract the District worked with PJHM Architects and clean fuel consultant Herbert Burnett of Burnett & Burnette to design the CNG station on the existing Maintenance & Transportation property. The District formally bid the project and awarded the Fueling Station Contract to GESI in March 2010.

Project Objectives

Provide 24 Time-fill and one (1) Fast-fill fueling station to service District buses as well as public, local government, local commerical, or future District vehicles.

Project Results Description

The station is complete and buses are being fueled on a daily basis. The District has also received interest from the City of Perris and CR&R, the local waste collection company, to use this station for vehicle refueling.

Project State
California
Project Status Description

The new refueling station opened on December 2, 2010 at the Perris Maintenance Facility located at the corner of Metz Road and A Street in the City of Perris.

Project Year
Summary Approved
No
Total Project Cost
$632,541.00
Co Funding Amount
$407,541.00
Contractor Address
155 East Fourth Street
Contractor Agency
Perris Union High School District
Contractor City
Perris
Contractor Contact
Anna Hamilton
Contractor Country
United States of America
Contractor State
CA
Contractor Phone
Contractor ID
0
Contractor Zip
92570
Co Participants
PJHM Architects
PCM Construction
Burnett & Burnette
Gas Equipment Systems Inc (GESI)
Bogh Engineering
Final Report Approved
No